How much energy does upgrading consume?
sourced
Electricity for CO2 separation runs roughly 0.18-0.30 kWh per cubic metre of raw biogas for PSA, 0.25-0.35 for water scrubbing, 0.2-0.4 for membranes and up to 0.4-0.6 for cryogenic routes. This parasitic load is a real cost line, not a rounding error.
- Source
- biogasupgradingplants.com; ifactoryapp.com
- sourced
- Traceable to a named source.
- Level
- Practitioner — Operating numbers, ranges and failure modes.
Where this shows up while you build
This answer is attached to the controls it explains, so it appears beside them in the builder rather than only here.