What is the approvals-to-commissioning critical path?

sourced

Broadly: secure the LOI, obtain Consent to Establish plus land and panchayat NOCs, run detailed engineering and construction, clear PESO and fire approvals, obtain Consent to Operate, then commission. Approvals run in parallel with engineering, and developers are repeatedly advised to map them before ordering equipment rather than after.

Source
IMARC Engineering; ManufacturingPlantIndia
sourced
Traceable to a named source.