sourced

Benchmarks vary by feedstock and offtake model. A 5 TPD plant commonly clusters around 20-30 crore rupees, or roughly 2-3 crore per TPD; the Standing Committee on Petroleum and Natural Gas cited 25-80 crore for a 100 TPD multi-feed plant; and GOBARdhan (2026) offers capital assistance up to 2 crore rupees per TPD against that.

Source
biogasflux; Renewable Watch; GOBARdhan PIB
sourced
Traceable to a named source.
Level
Investor & policyMoney, risk, and what the policy actually says.
Where this shows up while you build

This answer is attached to the controls it explains, so it appears beside them in the builder rather than only here.

Read next
Follow up

Answers come from this site's reviewed question bank and cite the entry they came from. Press / to focus. Not investment advice.

Something wrong with this entry?
What kind of problem is it with: What capex per TPD should a developer budget?
No account needed. Nothing is published.