What capex per TPD should a developer budget?
sourced
Benchmarks vary by feedstock and offtake model. A 5 TPD plant commonly clusters around 20-30 crore rupees, or roughly 2-3 crore per TPD; the Standing Committee on Petroleum and Natural Gas cited 25-80 crore for a 100 TPD multi-feed plant; and GOBARdhan (2026) offers capital assistance up to 2 crore rupees per TPD against that.
- Source
- biogasflux; Renewable Watch; GOBARdhan PIB
- sourced
- Traceable to a named source.
- Level
- Investor & policy — Money, risk, and what the policy actually says.
Where this shows up while you build
This answer is attached to the controls it explains, so it appears beside them in the builder rather than only here.