Illustratively: feedstock pre-processing about 1.5 crore rupees, digester about 5 crore, upgrading about 4.5 crore, compression and cascade about 3 crore, civil and utilities about 2 crore, instrumentation and SCADA about 1 crore - totalling roughly 20-30 crore. Upgrading plus compression alone is 20-25% of capex.