Does the supply calendar change the simulated numbers?
sourced
No, and the panel says so on its face. The supply calendar is descriptive - it drives copy, calendars and advisory flags - while the engine runs a single steady-state design point at a flat rupees-per-tonne price. Monthly availability curves and storage carry move into the model at a later stage; until they do, the panel does not pretend otherwise.
- Source
- lib/builder/procurement.ts (PROCUREMENT_AFFECTS_SIMULATION)
- sourced
- Traceable to a named source.
- Level
- Practitioner — Operating numbers, ranges and failure modes.
Where this shows up while you build
This answer is attached to the controls it explains, so it appears beside them in the builder rather than only here.