What is the process envelope, and how do I read it?
sourced
It is the safe operating window for the digester, read from three numbers: HRT, OLR and blended C:N. The limits depend on the reactor. A CSTR is flagged when HRT falls below 18 days or OLR rises above 4 kg VS per cubic metre per day, and fails above 5; a plug-flow dry digester is flagged below 20 days or above 6, and fails above 8. Blended C:N is flagged outside 20-35 on either. Those limits exist because acidification from overloading is the failure that costs weeks of output.
- Source
- CBGSIM engine pack (digester thresholds); 99pt5
- sourced
- Traceable to a named source.
- Level
- Practitioner — Operating numbers, ranges and failure modes.
Where this shows up while you build
This answer is attached to the controls it explains, so it appears beside them in the builder rather than only here.