What was the SATAT LOI process, step by step?
sourced
Under SATAT, the earlier scheme, a developer responded to an OMC Expression of Interest, submitted project details, and on selection received a Letter of Intent, which was then the basis for site finalisation, financing and the commercial agreement. As of July 2025 the SATAT portal recorded 108 commissioned plants against 1,094 active LOIs - a gap worth understanding before assuming an LOI is a plant.
- Source
- IMARC Engineering
- sourced
- Traceable to a named source.
- Level
- Practitioner — Operating numbers, ranges and failure modes.