Who are the major CBG developers, and at what scale?

projection

Reliance laid the foundation on 2 April 2025 for the first of a planned 500 plants - Kanigiri in Andhra Pradesh, 475 acres, 139 crore rupees, 100 TPD - within a 65,000 crore rupee state programme. Adani Total Gas runs Barsana at 600 TPD feedstock; GPS Renewables builds EPC at scale with IOC and BPCL joint ventures; EverEnviro operates an Indore MSW plant of about 15 TPD. Most of the large figures are planned capacity, not operational.

Source
RIL press release 2 April 2025; Adani, GPS and EverEnviro releases
projection
A target or forecast. Not delivered capacity, and not a commitment.