Why should working capital and EPC warranties be sized carefully?
derived
Feedstock is often paid for well ahead of CBG and FOM receipts, and subsidy timing is uncertain, so undersized working capital distresses otherwise viable plants. On the contract side, insist on guaranteed methane recovery, guaranteed specific power consumption and a guaranteed outlet specification, each with a test protocol and a penalty attached.